Report_Id: 252024 Est NO 0009 |
Date:08/04/2025 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 252024 | Estimate Number | 0009 | Estimate Type | PROGRESS | ||
District Office | ELIZABETHTOWN (04300) Bagby, Brandon R. | ||||||
Contractor | LOUISVILLE PAVING COMPANY INC | ADDR SN 0 VC Code KY0035764 | |||||
15415 SHELBYVILLE ROAD | |||||||
LOUISVILLE , KY , 40245 | |||||||
Pay Period | 07/12/2025 TO 07/25/2025 | ||||||
Date Approved | 08/03/2025 | ||||||
Primary Proj Number | MP04700652501 | ||||||
Project No. | NHPM 0653(051), NHPM 0653(049), NHPM 0653(050) | ||||||
Primary County | HARDIN | ||||||
Name of Road | SONORA TO ELIZABETHTOWN (I-65) | ||||||
Description | BEGIN AT THE LARUE/HARDIN COUNTY LINE EXTENDING NORTH TO NEW CONSTRUCTION JOINT 0.264 MILES NORTH OF COX RUN CULVERT | ||||||
Date Let | 01/23/2025 | Formal Acceptance | |||||
Date Awarded | 02/04/2025 | Date Work Began | 03/28/2025 | ||||
Date Contract Executed | 02/18/2025 | Open To Traffic | |||||
Date NTP Issued | 02/18/2025 | Actual Completion Date | |||||
Current Contract Amount | $7,306,104.49 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $7,063,113.00 |
Total Earnings | $5,397,705.20 |
$4,967,343.64 |
$430,361.56 |
|
Percent Complete | 73.88 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $1,908,399.29 |
Gross Earnings | $5,397,705.20 |
$4,967,343.64 |
$430,361.56 |
|
Total Change Orders | $242,991.49 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $5,397,705.20 |
$4,967,343.64 |
$430,361.56 |
|||
Contract Id | 252024 | Change Order Summary |
County | HARDIN | ||||||
Estimate Nbr | 0009 | Project Number | NHPM 0653(051), NHPM 0653(049), NHPM 0653(050) | |||||||
Contractor | LOUISVILLE PAVING COMPANY INC | Period | 07/12/2025 TO 07/25/2025 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
001 | Queue Warning System | Approved | 04/29/2025 | $5,104.75 | 0.0 | |||||
002 | Queue Warning System 2 | Approved | 06/26/2025 | $237,886.74 | 0.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 252024 | COMMONWEALTH OF KENTUCKY |
County | HARDIN | ||||||
Contract Type | PALT PAVEMENT (WITH ALTERNATES) | TRANSPORTATION CABINET |
Primary Project Number | MP04700652501 | ||||||
Estimate Nbr | 0009 | Period | 07/12/2025 TO 07/25/2025 | |||||||
Contractor | LOUISVILLE PAVING COMPANY INC | |||||||||
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0005 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 240.000 | 240.000 | 5.00 | 1,200.00 | |||
0010 | MAINTAIN & CONTROL TRAFFIC (HARDIN COUNTY) | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 118,000.00 | 59,000.00 | |||
0015 | SHOULDER RUMBLE STRIPS | 02696 | LF | 6,400.00 | 15,524.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0020 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 3.000 | 3.000 | 424.00 | 1,272.00 | |||
0025 | PIEZOELECTRIC SENSOR (PLANNING LOOPS) | 04829 | EACH | 6.00 | 6.000 | 0.000 | 0.000 | 2,675.00 | 0.00 | |||
0030 | LOOP SAW SLOT AND FILL (PLANNING LOOPS) | 04895 | LF | 60.00 | 60.000 | 0.000 | 0.000 | 12.00 | 0.00 | |||
0035 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 114,550.00 | 114,550.000 | 115,321.000 | 115,321.000 | 0.65 | 74,958.65 | |||
0040 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 66,618.00 | 66,618.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0045 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 47,932.00 | 47,932.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0050 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,280.00 | 3,280.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0055 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 70.00 | 70.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0060 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 160.00 | 820.000 | 80.500 | 352.500 | 433.000 | 120.00 | 9,660.00 | 51,960.00 | |
0065 | OVERBAND CRACK SEALING | 23071EN | LB | 30,000.00 | 30,000.000 | 13,521.900 | 13,521.900 | 1.70 | 22,987.23 | |||
0070 | INLAID PAVEMENT MARKER | 24489EC | EACH | 1,134.00 | 1,134.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0075 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0080 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 1,134.00 | 1,134.000 | 748.000 | 748.000 | 15.32 | 11,459.36 | |||
0085 | QUEUE PROTECTION VEHICLE | 25075EC | HOUR | 150.00 | 150.000 | 0.000 | 0.000 | 57.11 | 0.00 | |||
0090 | FURNISH QUEUE PROTECTION VEHICLES | 25117EC | MONT | 2.00 | 5.000 | 2.750 | 2.750 | 8,968.51 | 24,663.40 | |||
0095 | PORTABLE QUEUE WARNING ALERT SYSTEM | 26136EC | MONT | 2.00 | 5.000 | 3.500 | 3.500 | 4,268.28 | 14,938.98 | |||
0100 | QUEUE WARNING PCMS | 26137EC | MONT | 6.00 | 25.000 | 17.500 | 17.500 | 1.00 | 17.50 | |||
0105 | QUEUE WARNING PORTABLE RADAR SENSORS | 26138EC | MONT | 12.00 | 30.000 | 21.000 | 21.000 | 1.00 | 21.00 | |||
0140 | MOBILIZATION FOR MILL & TEXT (HARDIN COUNTY) | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 25,000.00 | 25,000.00 | |||
0180 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0185 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 55.00 | 55.000 | 4.290 | 4.290 | 1.00 | 4.29 | |||
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0003 THINLAY | |||||||
0135 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 88.00 | 88.000 | 3.450 | 48.220 | 51.670 | 0.01 | 0.03 | 0.51 | |
0150 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 138,000.00 | 138,000.000 | 180,900.000 | 180,900.000 | 0.31 | 56,079.00 | |||
0155 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 8,500.00 | 8,500.000 | 419.420 | 7,431.290 | 7,850.710 | 7.50 | 3,145.65 | 58,880.32 | |
0160 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 8,500.00 | 8,500.000 | 419.420 | 7,431.290 | 7,850.710 | 100.00 | 41,942.00 | 785,071.00 | |
0175 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 26.630 | 26.630 | 250.00 | 6,657.50 | |||
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0004 DEMOBILIZATION | |||||||
0165 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 165,000.00 | 165,000.00 | |||
0170 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.68 | 0.00 | |||
SUBTOT | $54,747.68 |
$1,359,170.75 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0175 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 256.000 | 256.000 | 5.00 | 1,280.00 | |||
0180 | MAINTAIN & CONTROL TRAFFIC (HART COUNTY) | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 100,000.43 | 50,000.21 | |||
0185 | SHOULDER RUMBLE STRIPS | 02696 | LF | 15,600.00 | 26,823.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0190 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 4.000 | 4.000 | 424.00 | 1,696.00 | |||
0195 | PIEZOELECTRIC SENSOR (PLANNING LOOPS) | 04829 | EACH | 12.00 | 12.000 | 0.000 | 0.000 | 2,675.00 | 0.00 | |||
0200 | LOOP SAW SLOT AND FILL (PLANNING LOOPS) | 04895 | LF | 120.00 | 120.000 | 0.000 | 0.000 | 12.00 | 0.00 | |||
0205 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 271,180.00 | 271,180.000 | 245,181.000 | 245,181.000 | 0.65 | 159,367.65 | |||
0210 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 160,596.00 | 160,596.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0215 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 110,584.00 | 110,584.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0220 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,050.00 | 3,050.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0225 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 110.00 | 110.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0230 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 160.00 | 820.000 | 93.500 | 333.500 | 427.000 | 120.00 | 11,220.00 | 51,240.00 | |
0235 | OVERBAND CRACK SEALING | 23071EN | LB | 90,000.00 | 90,000.000 | 41,820.000 | 41,820.000 | 1.70 | 71,094.00 | |||
0240 | PAVE STRIPE-WET REF TAPE-6 IN Y | 23871EC | LF | 410.00 | 410.000 | 0.000 | 0.000 | 8.00 | 0.00 | |||
0245 | PAVE STRIPE-WET REF TAPE-6 IN W | 23872EC | LF | 615.00 | 615.000 | 0.000 | 0.000 | 8.00 | 0.00 | |||
0250 | INLAID PAVEMENT MARKER | 24489EC | EACH | 2,567.00 | 2,567.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0255 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0260 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 2,567.00 | 2,567.000 | 1,521.000 | 1,521.000 | 15.32 | 23,301.72 | |||
0265 | QUEUE PROTECTION VEHICLE | 25075EC | HOUR | 150.00 | 150.000 | 127.500 | 58.000 | 185.500 | 57.11 | 7,281.52 | 10,593.90 | |
0270 | FURNISH QUEUE PROTECTION VEHICLES | 25117EC | MONT | 2.00 | 5.000 | 2.500 | 2.500 | 8,968.51 | 22,421.27 | |||
0275 | PORTABLE QUEUE WARNING ALERT SYSTEM | 26136EC | MONT | 2.00 | 5.000 | 2.500 | 2.500 | 4,268.28 | 10,670.70 | |||
0280 | QUEUE WARNING PCMS | 26137EC | MONT | 2.00 | 25.000 | 12.500 | 12.500 | 1.00 | 12.50 | |||
0285 | QUEUE WARNING PORTABLE RADAR SENSORS | 26138EC | MONT | 6.00 | 30.000 | 15.000 | 15.000 | 1.00 | 15.00 | |||
0320 | MOBILIZATION FOR MILL & TEXT (HART COUNTY) | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 25,000.00 | 25,000.00 | |||
0360 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0365 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 130.00 | 130.000 | 105.330 | 105.330 | 1.00 | 105.33 | |||
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0003 THINLAY | |||||||
0315 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 232.00 | 232.000 | 6.000 | 67.780 | 73.780 | 0.01 | 0.06 | 0.73 | |
0330 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 325,000.00 | 325,000.000 | 383,289.500 | 383,289.500 | 0.31 | 118,819.74 | |||
0335 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 22,700.00 | 22,700.000 | 3,224.300 | 15,852.360 | 19,076.660 | 7.50 | 24,182.25 | 143,074.95 | |
0340 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 22,700.00 | 22,700.000 | 3,224.300 | 15,852.360 | 19,076.660 | 100.00 | 322,430.00 | 1,907,666.00 | |
0355 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 105.350 | 105.350 | 250.00 | 26,337.50 | |||
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0004 DEMOBILIZATION | |||||||
0345 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 165,000.00 | 165,000.00 | |||
0350 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.66 | 0.00 | |||
SUBTOT | $365,113.83 |
$4,146,867.98 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0355 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 32.000 | 32.000 | 5.00 | 160.00 | |||
0360 | MAINTAIN & CONTROL TRAFFIC (LARUE) | 02650 | LS | 1.00 | 1.000 | 0.100 | 0.500 | 0.600 | 105,000.00 | 10,500.00 | 63,000.00 | |
0365 | SHOULDER RUMBLE STRIPS | 02696 | LF | 5,100.00 | 5,100.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0370 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0375 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 127,750.00 | 127,750.000 | 138,387.000 | 138,387.000 | 0.65 | 89,951.55 | |||
0380 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 74,538.00 | 74,538.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0385 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 53,212.00 | 53,212.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0390 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,520.00 | 3,520.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0395 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 180.00 | 180.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0400 | OVERBAND CRACK SEALING | 23071EN | LB | 35,000.00 | 35,000.000 | 26,558.100 | 26,558.100 | 1.70 | 45,148.77 | |||
0405 | INLAID PAVEMENT MARKER | 24489EC | EACH | 1,200.00 | 1,200.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0410 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0415 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 1,200.00 | 1,200.000 | 809.000 | 809.000 | 15.32 | 12,393.88 | |||
0450 | MOBILIZATION FOR MILL & TEXT (LARUE) | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 25,000.00 | 25,000.00 | |||
0480 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0485 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 55.00 | 55.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0003 THINLAY | |||||||
0440 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 6.030 | 6.030 | 250.00 | 1,507.50 | |||
0445 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 89.00 | 89.000 | 4.030 | 35.680 | 39.710 | 0.01 | 0.04 | 0.39 | |
0460 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 155,000.00 | 155,000.000 | 180,227.500 | 180,227.500 | 0.31 | 55,870.52 | |||
0465 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 8,650.00 | 8,650.000 | 8,909.810 | 8,909.810 | 7.50 | 66,823.57 | |||
0470 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 8,650.00 | 8,650.000 | 8,909.810 | 8,909.810 | 100.00 | 890,981.00 | |||
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0004 DEMOBILIZATION | |||||||
0475 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.66 | 0.00 | |||
SUBTOT | $10,500.04 |
$5,397,705.17 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |